The Zimbabwe Electricity Supply Authority (ZESA) is working on a strategy to end load-shedding by next year and achieve universal electricity access by 2030.
Key activities and timelines include: -commissioning at least six power projects, adding 2,690MW of new capacity by December 2025.
This would witness groundbreaking for three new power stations next month:
2025: Commission six power projects, adding 2,690MW of capacity.
2026: Clear the backlog of new power connections.
2027: End power imports.
2028: Become a net exporter of power.
2029: Achieve world-class power infrastructure.
2030: Achieve universal access to electricity.
Current and Projected Capacity:
1. Current dependable capacity: 1,500MW (can drop to as low as 1,000MW).
- New power stations: 9 new projects, starting soon, adding 1,000MW from captive power plants.
Key Measures:
1. Rebunde ZESA companies to improve efficiency.
- Shift large energy consumers (e.g., mining and smelting sectors) to self-supply electricity.
-
Manufacture cables and conductors locally (replace 24,000km of aging cables).
Challenges:
1. Impact of sanctions limiting concessionary loans.
2. Kariba Hydropower struggles (loss of capacity, producing just 150MW from a 1,050MW rated station).
3. Hwange Thermal Power Plant reliability issues due to age (over 45 years old).