The Zimbabwe Electricity Supply Authority (ZESA) is working on a strategy to end load-shedding by next year and achieve universal electricity access by 2030.
Key activities and timelines include: -commissioning at least six power projects, adding 2,690MW of new capacity by December 2025.
This would witness groundbreaking for three new power stations next month:
2025: Commission six power projects, adding 2,690MW of capacity.
2026: Clear the backlog of new power connections.
2027: End power imports.
2028: Become a net exporter of power.
2029: Achieve world-class power infrastructure.
2030: Achieve universal access to electricity.
Current and Projected Capacity:
1. Current dependable capacity: 1,500MW (can drop to as low as 1,000MW).
Key Measures:
1. Rebunde ZESA companies to improve efficiency.
Manufacture cables and conductors locally (replace 24,000km of aging cables).
Challenges:
1. Impact of sanctions limiting concessionary loans.
2. Kariba Hydropower struggles (loss of capacity, producing just 150MW from a 1,050MW rated station).
3. Hwange Thermal Power Plant reliability issues due to age (over 45 years old).
Kaizer Chiefs coach Cedric Kaze has urged patience and composure after the club’s poor run… Read More
Kaizer Chiefs have suffered a major setback with two experienced players injured. Both Brandon Petersen… Read More
Premier Soccer League giants Kaizer Chiefs have reportedly set their sights on Nigeria international goalkeeper… Read More
Kaizer Chiefs’ preparations for the Soweto Derby were severely disrupted before kick-off, a reality that… Read More
Kaizer Chiefs registered a second successive victory in the CAF Confederation Cup group stages after… Read More
Across Africa, vehicle buyers and importers are discovering a new way to connect — through … Read More