The Hwange 7 and 8 expansion project is now 82.3 percent complete and the commissioning of Unit 7 is expected to take place in November 2022.
Meanwhile, the commissioning of unit 8 is also expected in March 2023.
Meanwhile, the Deputy Chief Secretary to the Office of the President and Cabinet Eng Marawa toured the Hwange 7 & 8 project.
His tour took place on the sidelines of the ongoing International Renewable Energy Conference 2022 in Victoria Falls.
Zimbabwe is contending with electricity shortages with the power utility resorting to loadshedding.
Apparently, energy is one of the key drivers of the economy world over.
Zwnews
Buying a car in South Africa and bringing it into Zimbabwe through Beitbridge has become… Read More
For years, our platform has been your trusted destination for breaking football news, match updates,… Read More
Across Africa, vehicle buyers and importers are discovering a new way to connect — through… Read More
Cars for sale in Lesotho are now easily available to consumers with different budgets. Moreover,… Read More
The Zimbabwe Republic Police (ZRP) confirms a fatal road traffic accident which occurred on 23/10/25… Read More
Zimbabwe's state security agency, Central Intelligence Organisation (CIO) has burst an intricate WhatsApp-based scam through… Read More